Last updated 2010-08-27 14:07:04
Configuration Change, work starts on the aircraft on Friday 10th September.
Remove some chemistry instruments and replace with cloud physics/radiation/aerosol instruments.
Remove: FAGE & inlet, Peroxide/Formaldehyde, LIF & inlet, BBCEAS & inlet, CCN rack (to refit CCN etc), JO1D, JNO2.
Piero will be on site on Friday 10th September to aid removal of LIF.
Leeds will be on site on Friday 10th September to aid removal of FAGE.
Fit: CIP25, CIP100, CPI, 2DS, CAPS, 2DC, SID2, Manchester Cloud Rack, SHIMS, SWS rack and head, Radiometers 1 rack, Radiometers 2 rack, ARIES, VACC rack, CCN/CPC/FWVS rack, dropsonde launch tube.
Move: PTRMS to Peroxide/Formaldehyde position
VACC is in the FAAM stores.
The Met Office will deliver SWS, SHIMS and ARIES on Wednesday 8th September.
Manchester visiting 9th September to deliver CAPS, 2DS, CPI and Manchester Cloud Rack.
Andy Wilson (Met Office), Jennifer Brooke (Leeds) arriving Monday 13th September to test radiometers and VACC.
Cambridge will visit on10th September (lunchtime) to help remove the BBCEAS rack should this be needed and to return BBCEAS to Cambridge.
Dave Oram will be working on PTRMS on Monday 13th September