BORTAS Configuration Change 28/06/2011 - Last day for the delivery of BORTAS instruments to FAAM 29/06/2011 - FENNEC Instrument Removal The following will be removed: AVAPS and dropsonde ejector CLoud Physics Rack and all 5 canister instruments ALABAMA Radiometer Racks 1 and 2 SWS/SHIMS Rack, SWS head and SHIMS BCP ARIES 30/06/2011 - 04/07/2011 - BORTAS Instrument Fit The following will be fitted: CIMS and the CIMS inlet PTRMS AMS LIF and the LTI/LIF/WAS racks Nitrate rack CO and FGGA onto the Core Chemistry rack York GCMS, pumps and inlet Gas stowage JNO2/JO1D Instrument Scientists please note: do not leave it to the last minute to come to FAAM to complete the installation of your instruments! FAAM will need help installing all the non-core instruments 04/07/2011 - complete BORTAS Instrument Fit, ISMAR ground testing 05/07/2011 - BORTAS test flight 06/07/2011 - BORTAS test flight